Part of the roofing business guide.
A roofing contract for a homeowner job needs the work described slope by slope, named materials, one price, payments tied to visible progress, a written rule for rotten decking, the permit, the warranty and the right to cancel. Copy the table, fill in the brackets and check the notices your state requires. This is general information, not legal advice.
Roofing disputes cluster at three points: the price assumed a sound deck, the deposit ran ahead of the work, or nobody said who pulled the permit. The clauses below close those gaps.
The roofing contract template
Each row is a heading. Put your wording in the third column and delete rows that do not apply.
| Clause | Cover | Sample wording |
|---|---|---|
| Parties | Legal business name, license number where your state requires one, address, phone, insurer; owner and property address | [Company], [License no.], [Insurer] |
| Work by slope | Each slope or section, the roof there now, what happens to it | Main house, all slopes (about [squares] squares): strip existing [shingles] to the deck and install new [system] |
| Layers and tear-off | How many layers are on now, whether all come off, disposal | Remove [number] layer(s) of existing roofing to the deck; haul away all debris |
| Named materials | Maker, product line, color, underlayment, flashing, vents, drip edge, nails | [Maker] [line] shingles, [color]; [synthetic] underlayment; new drip edge and pipe boots |
| Decking by the sheet | Price per sheet for replacing damaged decking, who approves it | Decking replaced at $[amount] per sheet once the owner approves in writing |
| Flashing and vents | Ridge vent, box vents, chimney, skylight and wall flashing: new or kept | Chimney and wall flashing replaced; existing skylights [reflashed / excluded] |
| Permit | Who applies and who pays | Contractor applies and pays for permit: [Yes / No] |
| Insurance-funded work | Whether an insurance claim pays, who deals with the adjuster, deductible, scope matching the claim | Owner files and manages the claim; owner pays the deductible; Contractor does not act as adjuster |
| Total price | One figure, what it covers, whether sales tax is in it | $[total], covering materials, labor, disposal and permit fees |
| Payments | Each payment, its amount and the progress that triggers it | $[deposit] at signing; $[amount] on material delivery; $[balance] after final walk-through |
| Dates | Estimated start and finish, and what moves them | Start about [date], weather permitting; about [number] working days |
| Changes | How changes are priced, approved and paid | No extra work begins until both sign a change order showing the cost |
| Yard and cleanup | Protecting landscaping and pool, daily cleanup, nail sweep, dumpster spot | Magnetic sweep of yard and driveway at completion |
| Warranty | Workmanship years and exclusions; the maker’s warranty and who registers it | [Number]-year workmanship warranty; maker warranty registered by [contractor / owner] |
| Notices | State lien notice, federal cancellation right | See the sections below |
| Signatures | Owner and contractor with dates | [Owner] [Date] / [Contractor] [Date] |
Download the roofing contract template as a Word document. Free, no sign-up. Fill in the parts in square brackets.
Writing the work and the materials
Describe the roof as you would walk it with the owner. Name each section, say what comes off and what goes on, and list the items people forget: underlayment, flashing, drip edge, pipe boots and vents. “Install new roof” gives the owner nothing to hold you to and you nothing to point back to.
Sample wording: “Contractor will tear off the existing roof covering from all listed slopes to the deck, inspect the deck, install [underlayment], install new [flashing and drip edge], and install [shingle line] in [color]. Contractor will remove and dispose of all debris.”
State how many layers are on the roof today and that all of them come off, or that you will lay over one, because the number changes labor and disposal. Name what sits outside the price: interior ceiling repair, gutters, solar panel removal and reinstall, and any section not listed.
Decking, priced by the sheet
The deck stays hidden until the old roof is gone, so write the rule beforehand. Sample wording: “If rotted or damaged decking, fascia or framing is found, Contractor will stop work on that area and give Owner a written change order showing the cost. Work there resumes after both parties sign.” Quote decking per sheet, with the rate in the contract, so the owner knows what a rotten patch will cost before tear-off starts.
Jobs paid by an insurance claim
When a storm claim funds the roof, the contract must say so. Texas gives a clear example of the limits. The Texas Department of Insurance page on roofing and insurance says a roofer may not act as a public adjuster on a claim for work the roofer also does, may not waive, rebate or absorb the policyholder’s deductible, and must include a notice that the policyholder pays the deductible in contracts of $1,000 or more that involve an insurance settlement. Other states have their own rules on adjusters and deductibles. Leave the claim to the owner and the adjuster, price your scope from your own inspection, and look up your state’s rules.
Payments, deposits and lien notices
Link each payment to something visible: materials delivered, tear-off finished, roof finished. Do not make the last payment due before cleanup and the walk-through.
States set deposit and start rules, and they differ. In Florida, a contractor who takes an initial payment above 10 percent of the contract price for residential repair or improvement must apply for permits within 30 days and start work within 90 days after the permits are issued, unless there is just cause or the owner agrees in writing to a longer period (Florida Statutes section 489.126, checked November 2026). The same section says a contractor who has received more than the value of the work done may not fail to perform any work for any 90-day period. Other states set their own limits or none, so check yours.
Florida also demands a lien notice in some contracts. A direct contract above $2,500 for improvements to a dwelling of up to four units must carry a signed, dated notice in capitalized, boldface type of at least 12 points (section 713.015, checked November 2026). Other states have their own lien notices, and some require a license number or registration statement in the contract. Your state licensing board lists them.
Cancellation, including the emergency exception
A roof sold at the kitchen table after your inspection is the kind of sale the FTC Cooling-Off Rule (16 CFR Part 429) addresses. The buyer may cancel until midnight of the third business day, so keep any waiver of that right out of the contract and give the notice form the rule requires. State law applies alongside the rule. Where your state gives the buyer an equal or longer right, follow that as well, and check your licensing board for its notice wording.
The rule has a narrow emergency exception. The buyer must have started the contact, the work must meet a bona fide immediate personal emergency, and the buyer must write, date and sign a separate statement describing the emergency and waiving the right to cancel. A leak you tarp on the first visit may qualify. A re-roof booked for next month does not.
Two warranties, two owners
The workmanship warranty is yours. Give the number of years, what it covers (leaks from your installation, flashing you installed) and what it does not (storm damage, foot traffic, other trades). The maker’s warranty belongs to the maker: say who registers it and whether any registration fee is in the price. Write both into the contract.
Checks before sending
- Every slope in the estimate appears in the contract description.
- Each payment matches work the owner can see.
- The lien notice, license number and cancellation notice your state requires are on the document.
- The date the price holds until is on the estimate.
For laying out the estimate, see how to write a quote a homeowner can say yes to. Quote acceptance covers wording that gets a yes in writing, and the follow-up email after a quote helps when the estimate goes quiet. More on finding homeowners for roofing work is in roofing marketing.
If you want someone to follow up estimates once they are out, PreBuild Systems does that on the quotes page. Roofing is not among the trades we run in the United States.
Common questions
What belongs in a roofing contract?
Parties and license number, the work by slope, layers to remove, named materials, one total price, payments tied to progress, the permit, a decking rule, dates, warranty and any notice your state requires.
How large a deposit can a roofer ask for?
It depends on the state, and some set no limit. In Florida, a contractor taking more than 10 percent of the contract price as a first payment must apply for permits within 30 days and start within 90 days of the permits, unless there is just cause or the owner agrees in writing. Check your state.
Can a homeowner cancel a roofing contract?
Often. The FTC Cooling-Off Rule gives three business days to cancel a home-solicited sale of $25 or more, and you must hand over the cancellation notice form. Your state may add rights.
Can a roofer handle an insurance claim and the deductible?
Rules are set by each state. In Texas, the Department of Insurance says a roofer may not act as public adjuster on work the roofer performs and may not waive or absorb the deductible. Check your state.
Does a roofing contract have to be in writing?
Some states require a written home improvement contract. California, for example, requires one for projects over $500 (CSLB). Put it in writing in any case. Write it down anyway, so the work, price and warranty do not rest on memory.