A punch list is the written list of small items left to fix or finish before a job is complete. Walk the job with the homeowner, write every item down with its location, agree who fixes what and by when, and tie the final payment to the list being closed.
What goes on a punch list, and what does not
A punch list holds work that was in the scope and is not finished, or is finished badly. Typical items: a paint touch-up, a door that rubs, a missing cover plate, a caulk line that skipped, a scratch in a finished surface, a tile with a chipped edge.
It does not hold new work. If the homeowner asks for a shelf that was never in the contract, that is a change order with a price, not a punch item. Keep the two lists separate and say so at the start of the walk-through. This one habit prevents the most common argument at the end of a job.
A punch list template you can copy
Put this in a spreadsheet or on a printed page on a clipboard. One row per item.
| No. | Room or area | Item (what is wrong, one action) | Trade or person | Photo | Due date | Done (initials, date) | Owner OK (initials, date) |
|---|---|---|---|---|---|---|---|
| 1 | Kitchen | Touch up paint at the left of the range hood | Painter | Yes | [date] | ||
| 2 | Hall bath | Adjust the door so it latches without rubbing | Carpenter | Yes | [date] | ||
| 3 | Exterior | Reseal the gap at the window trim, north side | Our crew | Yes | [date] |
At the top of the sheet, put:
- [Your business name], job address, homeowner name, contract number.
- Date of the walk-through and who attended.
- A line that reads: “Items on this list are corrections to work in the signed contract. Additional work is handled by written change order.”
- A line for the date the list is expected to be complete.
At the bottom, two signature lines: one for you, one for the homeowner, with the date. The signature means the list is complete as of that walk-through, not that the job is accepted.
How to run the walk-through
Do it in a fixed order and you will miss less.
- Do your own walk first. Go through the job a day or two before the homeowner does, with the template, and fix what you find. Showing up with a short list reads as care.
- Book the walk with the homeowner. Ask for 45 to 90 minutes with the person who decides. If a spouse is not there, items get added later.
- Start outside, work in, finish where the work was most visible. Same order every time.
- Write while you walk. Number each item, take a photo with a note, and read it back to the homeowner before moving on.
- Sort each item as you go. Punch item, change order, or maintenance. Say it aloud.
- Agree dates before you leave. Give a date for each item or group of items, and a date for the final check.
Use good light. Open windows and blinds. Check finishes from the angle the homeowner sees them, not only close up.
Close items quickly
A punch list drags when it sits. Send the written list the same day, with the photos, so everyone is looking at the same list. Group items by trade and schedule one visit per trade rather than ten small trips. Tell the homeowner when each visit is, and mark items done as they are done.
When the last item is complete, do a short final check with the homeowner and get the second signature. Photograph the finished items. Keep the signed list with the job file.
Tie the final payment to the list
The list only protects your final payment if the contract already says how it works. It has to be there before the job starts, not added on the day. Wording to consider with your attorney:
Final payment of $[amount] is due on [substantial completion / completion of the punch list], whichever Owner and Contractor sign. Owner may withhold up to $[amount or percent] for items on a written punch list until those items are complete.
Two points worth deciding up front. First, a cap on what the homeowner can hold back, so a minor item cannot hold up the whole balance. A reasonable figure is the value of the open items, plus a margin you agree on. Second, a time limit: items not raised at the walk-through within a stated number of days do not hold the final payment.
Rules on retainage, final payment and lien deadlines are set by state law and by your contract, and they differ. Check your state licensing board’s page for home improvement contracts and have an attorney review your standard terms. This article is not legal advice.
When the homeowner adds items later
It happens. Sort the new item the same way: was it in the scope and not done right, or is it new? If it is a defect, fix it and note it on the list. If it is new, price it as a change order. If it is normal wear or settling after you left, be polite and say what your warranty covers, in writing.
Your warranty terms belong in the contract and again in the handover, so there is something to point to. A written quote that lists exclusions helps here too, because it shows which items were never in scope.
Keep the list with the job
A tidy close-out is where reviews and referrals come from, and remodeling jobs in particular are remembered for their last two weeks. Keep the signed list, the photos and the dates in the same place as the rest of the job, the way you would keep track of inquiries and quotes. For more on the trade, see renovations and extensions. Before the job starts, a timely quote follow-up is what gets you the signed contract in the first place.
Common questions
Who writes the punch list, the contractor or the homeowner?
Both contribute. The contractor writes it on the walk-through with the homeowner and may add their own items. The homeowner reviews it and signs it. Anything the homeowner finds later is written down and sorted as a defect or a change order.
When is the punch list done?
When every item is marked complete and the homeowner has signed off on the final check. Your contract should define that moment and say what final payment depends on.
Can the homeowner hold back final payment over a punch list?
That is set by your contract and by your state’s rules. Put the holdback amount and the time limit in the contract before the job starts, and check your state.
Is a punch list the same as a snag list?
Yes. Snag list is the term used in some countries. In the United States, punch list is the common term.