A concreting quote template lists each pour by area in square metres, the thickness and strength of concrete, the base and reinforcement, the finish, the preparation (excavation, formwork, levels), pump or barrow access, curing, and what is excluded. Copy the table below and fill in the square brackets for every slab, path or driveway on the job.
Concrete is priced from the measurements, but disputes start with the things the measurements do not show: the ground under the slab, the fall to the drain, the reach from the truck, and what “finish” meant. The template puts each on its own line. The general layout is in a quote template for builders and tradies; this page is for concreters.
The concreting quote template
Quote each area as its own row group (driveway, patio, path, shed slab). Different areas often carry different thickness, finish and access.
| Section | What goes in it | Example wording |
|---|---|---|
| Header | Business, licence number where your state requires one, ABN, insurance, phone, email | [Your business name], [Licence no.], [ABN] |
| Client and site | Client, address, date, quote number | [Client name], [Address], [Date], Quote [no.] |
| Area | Name of the pour, dimensions, total m2, shape, what it will be used for | [Driveway], [length x width], [m2], used by [cars / trailer / foot traffic] |
| Demolition and removal | Existing slab or path to break out, area, thickness, disposal | Break out [m2] of [existing], remove spoil to [tip / site] |
| Excavation and levels | Depth to dig, fill, compaction, falls and drainage, retaining at edges | Excavate to [depth]; fall of [x] toward [drain]; compacted [crushed rock] base |
| Formwork | Edge boxing, steps, expansion joints, isolation to buildings | Timber / steel form to [edges]; isolation joint to house |
| Concrete specification | Strength grade, slump or mix, additives, colour, supplier | [Strength] concrete from [supplier], [colour oxide / none] |
| Thickness and reinforcement | Slab thickness, mesh or bar, bar chairs, edge beams, vapour barrier | [Thickness] mm slab, [mesh type], on [chairs], [membrane under] |
| Finish | Broom, exposed aggregate, stencilled, honed, burnished, sealed; control joints | [Finish] with [saw cut / tooled] joints at [spacing] |
| Pump or barrow | Truck access, distance from the street, pump hire, wheelbarrow labour | Pump required: Y/N. Truck access via [route] |
| Council and approvals | Crossover or kerb work, road reserve, permits, who applies and pays | [Client / us] to apply for [permit]. Fees paid by [client] |
| Services and obstructions | Pits, pipes, power, trees, stormwater, irrigation | Client to mark [services] before [date]. Obstructions found: priced when found |
| Weather | What happens if rain or heat stops the pour, rebooking charge for trucks | Pour moves in wet weather; truck cancellation fee passed on: Y/N |
| Curing and protection | Curing method, days before foot traffic and vehicles, sealing, covering | Cured by [method]; no vehicles for [days] after the pour |
| Clean-up | Wash-out location, spoil removal, lawn and garden repair | Wash-out on site: Y/N. Lawn repair: [excluded / included] |
| Exclusions | See the list below | As listed |
| Price | Total and price per area, GST included or added | $[total] [including / plus] GST |
| Timing | Start window, pour day, finishing time, cure period | Start [window]; pour [date]; finishing [hours] |
| Payment | Deposit, on formwork, on pour, on completion | [Deposit] on acceptance; [balance] on completion |
| Validity and acceptance | Date the price holds to, how to accept | Price held until [date]. Accept by signing below |
Download the concreting quote template as a Word document. Free, no sign-up. Fill in the parts in square brackets.
Square metres, thickness and what each changes
The area sets the volume of concrete and the hours of finishing. Thickness changes the volume and the digging. The base and reinforcement change the preparation time. The finish changes the labour more than the concrete. Keep each as a line so a client who asks to drop a finish or add a section sees which line moves. For the cost side of a quote, the method in how to quote a job applies: price the hours and materials, then check the number against the last three similar jobs you did.
Write the measurements as you took them, with the unit. Do not give a rate per square metre without saying what is in it. A rate that covers excavation, base, mesh, concrete, pour and finish is a different number from a rate for the pour alone, and a client comparing quotes needs to know which one they are looking at.
Crossovers, kerbs and the road reserve
If the driveway meets the street, the part in the road reserve is usually the council’s concern, not just the owner’s. The rules are set by each council and state, so quote what you know and tell the client to check the rest. As one example, Sunshine Coast Council in Queensland says council approval is required for work on roads including the verge, that a new driveway or work in the verge may need approval, and that a “standard” crossover (where every checklist question is answered yes) can start construction while a “non-standard” one may need operational work approval, with construction not starting until the final approval notice. It also says that as property owner you are responsible for construction and maintenance of the whole driveway and crossover, and that on a state-controlled road you contact the Queensland Department of Transport and Main Roads. Fees apply to the applications. Source: Sunshine Coast Council, construction of vehicle crossovers and driveways.
That is one council. Others differ on what is standard, which forms apply and what they charge, so on the quote write who is applying, who is paying and what happens to the start date if approval is slow. If you do not want to apply, say “client to obtain approval” and set a date for it.
Weather, trucks and the pour day
A pour day has many people and a truck on a clock. Put on the quote what you do if rain stops the pour and whether a rebooking fee for the truck or pump is passed on. Put the finishing time too: a client who sees “pour at 7, finishing until mid-afternoon” understands why the drive is blocked.
Curing and the days after
State how the slab is cured and how many days before foot traffic, vehicles and loads. Use the number you actually give your clients. Add a line that cracking can occur in concrete and say what you do about control joints, so that expectation is set before the pour and not argued after. Keep these notes to one or two short sentences each.
Exclusions to copy and edit
- Removing trees, roots, stumps or large rocks found in the dig.
- Repair of underground services not marked before the work.
- Stormwater or drainage work not listed.
- Lawn, garden, paving and fence repairs from truck access.
- Council, certifier and road reserve fees unless listed.
- Colour and surface variation inherent in the product, unless a sample was agreed.
- Sealing, unless listed.
After you send it
Concreting quotes are often compared by price alone. A call after a day or two, and a short follow-up after that, is the cheapest way to be remembered: follow-up email after a quote. PreBuild also follows up quotes for trades.
Common questions
What should a concreting quote include?
Each area in square metres, demolition and excavation, base and reinforcement, concrete grade and thickness, finish, access and pump, approvals, weather terms, curing, exclusions, the price, timing, payment stages and the date the price holds to.
Should I quote concrete per square metre?
You can, if the quote says what the rate includes. Show excavation, base, reinforcement and finish as part of it, or as separate lines, so the client can compare like with like.
Who applies for the council crossover permit?
Agree it on the quote. Some concreters apply on the client’s behalf; others leave it to the owner. The council page decides what is needed, so check your council.
What happens if it rains on pour day?
Write it down before the job. Say the pour moves, say who pays for cancelled trucks or pumps, and say how the new date is set.
How do I price hidden problems like rock or old services?
Put them in as exclusions or as a stated rate that applies when found, so the client has read it before the dig.