A change order is a written agreement, signed by you and the owner before the extra work starts, that says what is changing, what it costs and how it moves the schedule. A template you can copy is below. The rule that gets extras paid is short: written, priced, time impact stated, signed before work.
Change order template
Copy this into your own document or software. Replace everything in square brackets.
| Field | What to write |
|---|---|
| Change order no. | [CO-001, numbered in order for this job] |
| Date | [Date written] |
| Project and address | [Job name and site address] |
| Owner | [Owner name] |
| Contractor | [Your business name, license no. if your state issues one] |
| Original contract | [Contract date and original price: $____] |
| Reason for change | [Owner request / hidden condition found / design changed / code requirement] |
| Description of work | [What will be done, where, with which materials and finishes. Say what is not included.] |
| Price change | [Add / deduct $____, showing labor, materials, subcontractors, markup and tax] |
| Time change | [Add / deduct ____ working days. New completion date: ____] |
| Effect on payments | [How this amount is billed: added to the next payment / paid at completion of this item / paid before work starts] |
| Revised contract price | [Original price + approved change orders + this one = $____] |
| Approval | Owner: [name, signature, date]. Contractor: [name, signature, date]. Work covered by this order will not start until both have signed. |
Download the change order template as a Word document. Free, no sign-up. Fill in the parts in square brackets.
Everything else in the original contract stays as written. Add that sentence at the bottom.
How to use it so extras get paid
The form is only half of it. The habit is what collects the money.
Write it down before you touch it
The most common unpaid extra starts with “while you are here, could you also…”. Say yes to the conversation and no to the work until the form is signed. Do it on your phone at the site if you have to, and send it from there.
Price it so the owner can follow the number
Show the labor, materials, subcontractor cost and your markup as separate lines. An owner who sees how the number was built argues less about it. Include your sales tax where it applies to the item. If you cannot price the work yet because you have to open a wall, use a not-to-exceed number or a time-and-materials rate with a cap, and say so on the form.
State the time, even if it is zero
Write “no change to completion date” if that is the case. If it adds days, write the number. A change order that moves money but not the schedule leaves you arguing about the schedule at the end.
Get both signatures before work starts
Some states put this in law. California’s contractor board says a change order is not enforceable against the buyer unless it identifies, in writing before the work starts, the scope of work, the amount added or subtracted from the contract, and the effect on the progress payments or the completion date. It also says the owner may not require the contractor to do extra work without giving written authorization before that work starts. A contractor who misses these steps may still recover payment under legal or equitable remedies designed to prevent unjust enrichment (CSLB sample home improvement contract). That is California. Your state may be looser or stricter, and some leave it to the contract, so look up your state contractor board.
Keep a running total
List every change order on one page with its number, amount and date. Send the owner the updated total each time. By the end of the job, the revised contract price should not surprise anyone.
Bill it and follow up
Put the change order on your next invoice as its own line, with its number. If the owner goes quiet on signing, follow up the same day. A short follow-up email works as well for a change order as for a quote.
When a change order is the right tool
- The owner asks for something new. More outlets, a different tile, a bigger deck.
- You find a hidden condition. Rot, old wiring, a pipe not on the drawing.
- A code or inspector requirement adds work that was not in the original scope.
- Materials change. An allowance runs out, or a product is discontinued and the owner picks another.
- The owner removes something. A deduct change order protects the final number too.
If you need to quote the original scope clearly in the first place, how to write a quote and getting a yes in writing go with this.
What to do when the owner will not sign
Stop work on the extra and carry on with the rest of the contract. Tell the owner in writing what you would have done, what it would cost and that you have not started. Do not give the work away to keep the peace on a job that has months left. If it keeps happening, the contract needs a clause that says all changes need a signed change order, and your estimating needs to find what is missing earlier. See estimating for small builders. If extras and quotes both go quiet, see how follow-up on quotes works.
Common questions
Does a change order have to be signed?
It should be, before the work starts. In California, the contractor board says an unwritten or incomplete change order is not enforceable against the buyer. Other states differ, but a signature is always your best proof.
What should a change order include?
The description of the work, the amount added or deducted, the effect on the schedule and payments, the revised contract price, and both signatures with dates.
Can I charge for a change order if the owner only agreed verbally?
Maybe, but you will be arguing from memory. Where the law requires written change orders, you may lose the right to enforce the extra. Get it in writing.
Is a change order the same as an estimate?
No. An estimate is your price for work not yet agreed. A change order is the signed agreement that adds or removes work from a contract already in place.