Part of the renovation business guide.
A kitchen renovation quote template lists the job in the order it happens: strip-out, rough-in plumbing and electrical, cabinetry, benchtops, splashback, appliances, final fix and clean. It shows cabinets and benchtops as defined items, appliances and taps as allowances, and says what the client must have decided by when. Copy the table below and fill in the square brackets.
Kitchens go wrong at the handover points: the benchtop cannot be cut until the cabinets are in, the splashback waits for the benchtop, and the plumber cannot connect until the sink is set. A quote that shows those steps tells the client why the job takes the time it does. The general layout is in a quote template for builders and tradies; this one is for kitchens, including jobs where a joiner supplies the cabinets and you run the rest.
The kitchen renovation quote template
| Section | What goes in it | Example wording |
|---|---|---|
| Header | Business, licence number, ABN, insurance, phone, email | [Your business name], [Licence no.], [ABN] |
| Client and site | Client, address, date, quote number, floor level, access | [Client name], [Address], [Date], Quote [no.] |
| Existing kitchen | Size, layout, wall and floor construction, what stays, known problems | [Layout], [wall type], existing floor [type] to stay or be replaced |
| Design basis | Drawing or layout number, who produced it, date, what the price is based on | Price based on [drawing no., date]. A change to the layout is a variation |
| Strip-out and removal | Cabinets, benchtops, appliances, splashback, flooring, rubbish removal, what the client keeps | Remove and dispose of [list]. Client keeps [list] |
| Walls, ceiling and floor | Wall repair, ceiling patching, new flooring, rangehood duct, structural changes | [Repair wall at removed pantry], [flooring: included / by others] |
| Cabinetry | Supplier or joiner, carcass material, door and panel finish, hardware, soft close, number of drawers and doors, pantry, bin, corner units | [Supplier]: carcass [material], doors [finish, colour], hardware [brand or grade] |
| Benchtops | Material, thickness, edge profile, cut-outs (sink, cooktop, tap holes), who templates and when, waterfall ends | [Material, colour] benchtop, [edge], cut-outs for [list]. Templated after cabinets are fixed |
| Splashback | Material, height, area, power point cut-outs, behind the cooktop | [Tiles / glass / stone], [height] above bench, [m2] |
| Sink, tap and waste | Sink type and size, tap, waste disposal, dishwasher connection, allowance or specified model | Allowance $[amount] for sink and tap, supply only |
| Appliances | Which are supplied by you, which by the client, delivery date, allowance or model and dimensions | Oven, cooktop, rangehood, dishwasher: allowance $[amount] / supplied by client by [date] |
| Plumbing | Moving the sink or dishwasher, new pipework, gas, who holds the licence | Licensed plumber [name, licence]: [list of connections] |
| Electrical | Power points, lighting, rangehood, oven circuit, under-cabinet lights, switchboard | Licensed electrician [name, licence]: [list] |
| Painting and finishing | Walls, ceiling, touch-ups, silicone, cleaning before handover | [Number] coats; final clean included: Y/N |
| Staging | Order of work, when the kitchen is unusable, temporary arrangements | Kitchen out of use from [stage] to [stage]; client sets up [temporary sink] |
| Client decisions | List of selections with the date each is needed | Benchtop colour by [date]; appliances by [date]; tiles by [date] |
| Exclusions | See the list below | As listed |
| Price | Total, cabinetry, benchtops and trades shown separately, allowances shown separately, GST basis | $[total] [including / plus] GST, of which allowances $[amount] |
| Timing | Start, lead times for cabinets and stone, weeks on site | Start when cabinets are due on [date]; about [weeks] on site |
| Payment | Deposit (for cabinet order), stage payments tied to events, final payment | [Deposit] to order cabinets; [stage] on cabinets fixed; [balance] on completion |
| Validity and acceptance | Date the price holds to, how to accept | Price held until [date]. Accept by signing below |
Download the kitchen quote template as a Word document. Free, no sign-up. Fill in the parts in square brackets.
Cabinetry: say what the price buys
Two cabinet quotes at different prices are rarely the same kitchen. The carcass material, the door finish, the hardware and the number of drawers each change the price. The quote should state them, or refer to the joiner’s drawing and its number. When the client compares your quote to another, the lines they should be able to compare are carcass, doors, hardware and the count of drawers and doors.
If the cabinets are made to measure, the dimensions come from site measure after the old kitchen is out, or from careful measure before it. Write which one the price is based on, and what happens if the room is out. This is a risk to name, not to hide.
Benchtops and the sequence behind them
Stone and many engineered tops are templated once the cabinets are fixed, then cut and delivered. During that gap the kitchen has no bench. Put the lead time and the gap on the quote. Tell the client the date when the sink and cooktop will not be connected, so they do not hear it first on the day.
Appliances and fixtures as allowances
If the client has not chosen appliances, use an allowance, say what it covers (supply only, or supply and install), and give the date the choice is needed. If they supply their own, say so, and set the delivery date and the dimensions you need. A rangehood that does not match the duct, or a fridge space drawn for the wrong model, is a mistake that costs days. Allowances and how they adjust are explained in provisional sums and prime cost items.
Consumer Affairs Victoria defines a prime cost item as a fitting that is part of the contract, and a provisional sum as a reasonable estimate of the cost of certain work. Its page says a builder must include a reasonable allowance for supplying and delivering a prime cost item: Consumer Affairs Victoria, building definitions. That is Victorian; use the term your own state’s contract uses.
What a state says a written quote should show
The NSW Government says a written quote should include all the work to be done, list all the materials to be used and reflect the client’s specifications, and that variations to a contract must be in writing and signed by both parties: NSW Government, getting quotes. For a kitchen, “all the materials” means the brand or grade of each cabinet part, the benchtop and the splashback, not “kitchen supplied and installed”.
Exclusions to copy and edit
- Changes to the layout, or to appliance models after the drawing is signed.
- Asbestos testing or removal, if the existing wall or floor lining contains it.
- Repairs to rot, damp or structural faults found after strip-out, unless an allowance is stated.
- Upgrading the switchboard, the gas supply or the water supply.
- Flooring beyond the area listed, and repainting rooms beyond the kitchen.
- Delays caused by late supply of client-chosen items.
- Council, certifier or strata fees unless listed.
After you send it
Kitchen clients usually collect several quotes and take weeks to decide. A call after a few days, and a follow-up when the cabinet lead time starts to matter, keeps you in the running. See follow-up email after a quote and kitchen and bathroom renovation leads. PreBuild also follows up quotes for trades.
Common questions
What should a kitchen renovation quote include?
The existing kitchen and design basis, strip-out, cabinetry, benchtops, splashback, sink and tap, appliances, plumbing and electrical, finishing, staging, client decisions with dates, exclusions, the price, timing, payment stages and the date the price holds to.
Should appliances be in the kitchen quote?
Either as an allowance if you supply them, or as a note that the client supplies them with a delivery date and dimensions. Do not leave them out without saying so.
Who supplies the cabinets: me or the client?
Whoever you agree with the client. State it on the quote, along with who orders, who measures and who is responsible if the measure is wrong.
How do I quote a kitchen when the client has not chosen finishes?
Use allowances for the items still to be chosen, show them separately from the fixed items, and put a selection date on each. Say that choices above the allowance are added to the price.
Do I need a deposit for a kitchen?
Many kitchen jobs take a deposit so the cabinets can be ordered. The limit, if any, is set by state contract law, so check your state regulator’s page before you set the figure.