Part of the roofing business guide.
Job costing means recording what each job actually cost, in labor, materials, subcontractors and a share of overhead, and comparing it to what you estimated. Do it on every job, even on paper, and you will know which jobs make money and what to charge for the next one.
What job costing tells you that your bank balance does not
A healthy bank balance can hide a losing job. Money from a deposit on job B covers the shortfall on job A. Job costing separates them. It answers three questions: did this job make the profit I priced, which part of it went over, and is my price for the next one right?
Without it, contractors tend to find out at tax time that their repeat job is their worst job. With it, you find out two weeks in.
The four costs to track on every job
| Cost | What counts | How to record it |
|---|---|---|
| Labor | Hours worked times the loaded hourly cost (wage plus payroll costs). Include your own time at a fair rate. | Daily time sheet by job and task |
| Materials | Everything bought for the job, including delivery, dump fees and small consumables. | Receipts coded to the job on the day |
| Subcontractors | Sub invoices, including any change orders you agreed. | Sub invoices coded to the job |
| Other direct costs | Permits, equipment rental, dumpsters, inspections, fuel used for the job. | Receipts coded to the job |
Overhead sits on top and is covered below. The first discipline is the code: every receipt and every hour gets a job name and a category when it is recorded. If you wait until the end of the month you will not remember which truck load went to which house.
Set up a simple cost code list
Keep it short. A small remodeler or trade business can work with eight to twelve codes. For example:
- Demolition and disposal
- Framing and carpentry
- Electrical
- Plumbing
- Mechanical or HVAC
- Finishes (drywall, paint, tile, flooring)
- Permits and inspections
- Equipment and dumpsters
- Change orders
Use the same codes as the sections in your estimate. That is what makes the comparison work: your estimate said $4,000 for framing, and the actual cost to date under “Framing” is $5,100.
Find your labor burden
Your hourly wage is not your labor cost. Add payroll taxes, workers’ compensation, insurance that follows labor and any benefits you pay. Your accountant or payroll provider can give you the percentage. As an example only: a $30 wage with 30 percent on top costs $39 an hour. Your percentage will differ, so use your own.
Allocate overhead
Overhead is what you pay whether or not a job is running: the office, insurance, vehicles, software, phone and your own salary if it is not in labor. There are two common ways to put it on a job.
- A percentage of direct cost. Add up a year of overhead, divide by a year of direct job costs, and add that percentage to every job.
- A rate per labor hour. Add up a year of overhead, divide by the billable hours your crew works, and add that rate to each hour.
Either works. Pick one and keep it. The number only needs to be close, and you update it once or twice a year.
A worked example with made-up numbers
These figures are an example to show the method. They are not benchmarks. Replace them with yours.
| Line | Estimate | Actual | Difference |
|---|---|---|---|
| Labor (hours times loaded cost) | $9,000 | $10,800 | $1,800 over |
| Materials | $7,000 | $7,300 | $300 over |
| Subcontractors | $5,000 | $5,000 | $0 |
| Other direct costs | $800 | $1,100 | $300 over |
| Direct cost total | $21,800 | $24,200 | $2,400 over |
| Overhead at 15% of direct cost | $3,270 | $3,630 | |
| Total cost | $25,070 | $27,830 | |
| Price to the homeowner | $31,300 | $31,300 | |
| Profit | $6,230 | $3,470 |
The estimated profit was about 20 percent of the price. The actual was about 11 percent. Labor was the problem. That is the finding that matters: not “the job went over” but “labor ran 20 percent over, and here is the task code where it happened.” If it was demolition because the walls had hidden damage, you needed a change order. If it was tile because the crew is slower than your estimate assumed, you adjust your labor assumption on the next tile job.
Use the numbers to price the next job
After each job, spend 15 minutes on a short close-out:
- Where did actual cost differ from estimate by the most?
- Was it a one-off or will it happen again?
- Did every change get a signed change order and get billed?
- What number in the estimating sheet needs to change?
After five or ten similar jobs, you will have your own unit costs: your real cost per square foot of tile, per linear foot of fence, per bathroom. Those beat any national average because they come from your crew and your market. Our guides on estimating for small builders and how to quote a job show where those numbers go.
Margin check before you send an estimate
Costs include overhead, and the price must then carry your profit. If you want 20 percent profit on the price, divide total cost by 0.80, not by adding 20 percent. A 20 percent markup on cost gives a smaller margin than 20 percent on price. The difference is explained in markup vs margin.
How often, and with what tools
- Daily: hours and receipts, coded to the job. This is the habit that matters.
- Weekly, on bigger jobs: compare actual to estimate by cost code. If labor is at 70 percent of budget and the job is 40 percent done, you have time to act.
- At close-out: the 15-minute review above.
A spreadsheet works for a one- or two-crew business. Accounting software can code costs to jobs, and construction management tools add time sheets and budgets. Check that whatever you choose lets you code each cost to a job and a category, produces a report of estimate versus actual, and exports your data so you are not locked in. Estimates you send also deserve a follow-up system; see quote follow-up for that side.
Common questions
What is job costing in construction?
It is the process of tracking the actual labor, materials, subcontractor and other direct costs of each job, plus an allocation of overhead, and comparing them to your estimate to see the profit.
How do I do job costing without software?
Use a spreadsheet with a tab per job. Record each hour and receipt the day it happens, with a cost code. Add up by code weekly and compare to your estimate.
Should my own time be in the job cost?
Yes. If you work on the job, put your hours in at a fair rate. If you run the job without working on it, your supervision time belongs in overhead or in a project management line.
How is job costing different from estimating?
Estimating is what you expect a job to cost before you start. Job costing is what it did cost. Comparing the two is how your estimates get better.