Bathroom renovation quote template: stages, waterproofing and allowances

A copyable bathroom quote layout with the stages in order, waterproofing wording, fixtures as allowances and exclusions, plus what two state pages say about licensing and certificates.

Updated 24 November 2026 · For builders, trades and home services

Part of the renovation business guide.

A bathroom renovation quote template splits the job into stages (strip-out, structure, plumbing, waterproofing, tiling, fit-off), names who certifies the waterproofing, puts fixtures in as allowances, and lists what is not included. Copy the table below and fill in the square brackets.

Bathrooms are quoted badly in one way more than any other: a single lump sum with “supply and install bathroom” on it. When the tiles turn out to be dearer than the client assumed, or the floor under the old shower is rotten, nobody can say what was and was not in the price. The template below stops that. It sits alongside the general layout in a quote template for builders and tradies.

The bathroom renovation quote template

Section What goes in it Example wording
Header Business, licence number, ABN, insurance, phone, email [Your business name], [Licence no.], [ABN]
Client and site Client, address, date, quote number, which bathroom (main, ensuite, powder room) [Client name], [Address], [Date], Quote [no.], [Main bathroom]
Existing room Size, floor type, wall construction, shower type, age, known problems [Size], [slab / timber floor], [existing tiles on sheet / cement sheet]
Layout and scope What moves and what stays: shower, bath, vanity, toilet, window, door, heating Remove [existing]; install [new]. Fixtures stay in current positions: Y/N
Demolition Strip-out to what level, protection of the rest of the house, rubbish removal Strip to [frame / slab]; floors protected to [path]; skip included
Structure and carpentry Wall framing, floor repair, new flooring sheet, fall to the waste, hob or step-down, niche Replace [floor sheet]; repair rot found: [allowance $ / quoted when found]
Plumbing Moving or replacing taps, shower mixer, waste, toilet pan, hot water, who holds the licence Licensed plumber [name, licence]: [list of fixtures connected]
Electrical Lights, exhaust fan, heated rail, power points, heated floor Licensed electrician [name, licence]: [list]
Waterproofing Area covered (floor, walls up to what height, shower recess, junctions), membrane system, curing time, certificate Membrane to [floor and walls to height], by [licensed waterproofer, licence no.], with [certificate] issued on completion
Tiling Floor and wall tile area in m2, tile size, layout (stack, offset, pattern), grout, tile trims, who supplies tiles [m2] floor, [m2] walls to [height]. Tile allowance $[amount]/m2 supplied by [client / us]
Fixtures and fittings (allowances) Vanity, basin, tapware, shower screen, toilet, bath, mirror, accessories, with allowance for each Vanity: allowance $[amount] supply only. Tapware: allowance $[amount]
Painting and finishing Ceiling, walls above tile, doors, architraves, silicone [Number] coats, colour [by client]
Access and living Whether the home is lived in, water shut-offs, dust, working hours, another toilet available Water off for [days]; client has [second bathroom: Y/N]
Approvals Council or certifier approval needed or not, who applies, strata approval [Client / us] to confirm approvals for [work]
Exclusions See the list below As listed
Price Total, stage prices, GST included or added, total of allowances shown separately $[total] [including / plus] GST, of which allowances $[amount]
Timing Start, weeks on site, cure and inspection hold points Start [window]; about [weeks]; waterproofing cure [days] before tiling
Payment Deposit, stage payments tied to events, final payment [Deposit] on acceptance; [stage] after waterproofing certified; [balance] on completion
Variations How a change is priced and approved in writing Changes agreed in writing and priced before the work is done
Validity and acceptance Date the price holds to, how to accept Price held until [date]. Accept by signing below

Download the bathroom quote template as a Word document. Free, no sign-up. Fill in the parts in square brackets.

Waterproofing: who does it and who certifies it

Waterproofing is the part of a bathroom job that fails slowly and expensively, so the quote should say who is doing it, with what, and what paper you will hand over. The rules are state by state. Two examples from the state pages we read:

  • Queensland. The Queensland Building and Construction Commission lists a waterproofing certificate among the key certificates. It says the certificate (Form 43 or Form 12, depending on the circumstance) is required when waterproofing work exceeds $3,300, must be carried out and issued by a licensed contractor, and is essential for wet areas such as bathrooms, toilets and laundries, including floors and walls adjacent to showers, baths and other water fixtures. Source: QBCC, handover and final documentation.
  • New South Wales. NSW Government says waterproofing is any protective treatment of a home to prevent water or moisture getting into it, including protective treatment of wet areas such as a shower. A contractor licence is needed to carry out, advertise or contract for waterproofing work valued at more than $5,000 in labour and materials, including GST. The page we read does not mention a certificate of compliance, so ask Fair Trading what applies to yours. Source: NSW Government, waterproofing work.

We could not open an official certificate page for the other states, so we have left those out. Check your own state regulator before you put “certificate included” on a quote. Then write the line exactly as you can deliver it: the name and licence number of the person doing the membrane, the area covered, and the certificate you will give the client at the end.

Fixtures as allowances

Clients choose vanities, tapware and tiles after they sign. Put each as an allowance with a dollar amount and say whether it covers supply only or supply and fit. The tile allowance is the one that moves most, because the area is large. An allowance that is too low looks cheap now and costs you the argument later. How allowances adjust at the end, and why big ones cause trouble, is covered in provisional sums and prime cost items.

Consumer Affairs Victoria defines a prime cost item as a fitting that is part of the contract and a provisional sum as a reasonable estimate of the cost of certain work. It says a builder must include a reasonable allowance for supplying and delivering a prime cost item. That page is Victorian: building definitions. Use the term your state’s contract uses.

Exclusions to copy and edit

  • Repair of rot, termite damage or structural problems found after strip-out, unless stated as an allowance.
  • Asbestos testing or removal if the existing sheeting or tiles contain it.
  • Moving the toilet or shower to a new position, if not in the scope.
  • Replacement of hot water service, pipework beyond the room, or the main switchboard.
  • Tiles, tapware and fittings above the allowance, and the cost of delays caused by late supply.
  • Strata, council or certifier fees unless listed.
  • Repair of damage to flooring or walls outside the bathroom caused by access.

Sending it

Walk through the quote with the client on site if you can. Bathrooms are chosen with the eye, and a client who has seen the scope in the room signs faster than one reading it on a phone. If the quote sits, follow-up email after a quote has the wording, and kitchen and bathroom renovation leads covers how those businesses find work. PreBuild also follows up quotes for trades.

Common questions

What should a bathroom renovation quote include?

The existing room, the scope by stage, who does the plumbing, electrical and waterproofing, the tiling area, fixture allowances, approvals, exclusions, the price, timing, payment stages and the date the price holds to.

Who certifies bathroom waterproofing?

It depends on the state. In Queensland the QBCC page we read says a waterproofing certificate is required for work over $3,300 and must be issued by a licensed contractor. The NSW page we read covers licensing and does not mention a certificate. Check your own regulator.

Should tiles be a fixed price or an allowance?

If the client has not chosen tiles, use an allowance per square metre and say whether it covers supply only. If they have chosen, price those tiles and say so.

How do I handle rot found after demolition?

Say on the quote that hidden damage is not included, and either set an allowance or state that it will be priced when found and approved in writing before work continues.

How long should a bathroom quote stay valid?

Tile and fixture prices change, so put a date on it. Many businesses use a short window and re-price after it.

Want homeowners for your business?

Tell us your trade and where you work. We'll ring you to talk it through and give you your price in writing. If it's not a fit, we'll say so.

No retainer, no lock-in, nothing monthly.

We'll ring or text you about your application. No spam. Privacy

Pick 10, 15 or 20
No lock-in

Apply now